The State Grid Xuchang Power Supply Company Strives to Support Key Project Construction by Relocating Power Lines

|ChinaNews|Published:2024-11-22 10:48:41

The State Grid Xuchang Power Supply Company Strives to Support Key Project Construction by Relocating Power Lines

Staff members relocating power transmission lines (Photo by Jiao Yongsheng)

  Recently, the State Grid Xuchang Power Supply Company organized construction personnel to relocate the 110 kV Hao-Ge transmission line, fully supporting the construction of the Xuchang Ring Expressway. According to the expressway construction plan, the State Grid Xuchang Power Supply Company needs to relocate 93 power lines in total, with 89 relocations already completed.

  The Xuchang Ring Expressway is one of the key projects in Henan Province, China. It involves the construction of three expressways within Xuchang City: the Zhengzhou-Xuchang Expressway, Ring Expressway, and Jiaozuo-Pingdingshan Expressway. A total of 222 power line relocations are required, including 51 for the Zhengzhou-Xuchang Expressway, 93 for the Ring Expressway, and 78 for the Jiaozuo-Pingdingshan Expressway.

  During the relocation process, the State Grid Xuchang Power Supply Company exemplified the spirit of craftsmanship, benchmarked against advanced models in the State Grid system, and strengthened quality control throughout the entire process. They focused on improving technical standards and construction techniques, striving to create high-quality, model, and demonstration projects. They strengthened on-site risk assessments and safety management, strictly ensuring the quality of the project. By combining on-site inspections with remote monitoring, they made every effort to ensure the safety of both the worksite and the personnel, effectively ensuring that the relocation work was completed with high quality and efficiency. The Company also formulates power outage plans in a scientific and reasonable manner and reduces the planned power outage duration and frequency of 10-kilovolt distribution facilities, ensuring reliable power supply.

  Currently, the Company has completed 146 relocation projects, with the remaining 76 progressing as planned, making every effort to meet the needs of the expressway construction.

Share This Story
Explore ChinaNews
  • Tel:+86-010-68891122
  • Add:16A Shijingshan Road,China.100040

Copyright ©1997- by CRI Online All rights reserved