2019年11月8日,由國網湖北電科院負責調試的印尼芝拉扎三期工程百萬機組一次性通過168小時滿負荷試運行,正式投入商業運行。該工程位於印度尼西亞中爪哇省芝拉扎縣,裝機容量為1×100萬千瓦,全部使用中國電站設備和技術標準,是中國出口的首批百萬級火電機組之一,也是共建“一帶一路”倡議落地印尼的重要項目。
On November 8, 2019, the one-million-kilowatt generating unit of Indonesia's Cilacap III Project, commissioned by the State Grid Hubei Electric Power Research Institute, successfully completed its 168-hour full-load trial operation in a single attempt and was officially put into commercial operation. Located in Cilacap County, Central Java Province, Indonesia, the project has an installed capacity of 1×1 million kilowatts, fully adopting Chinese power equipment and technical standards. It is one of the first million-kilowatt coal-fired power units exported by China and a significant BRI project implemented in Indonesia.
出品|中央廣播電視總臺國際在線 國網湖北省電力有限公司
指導單位|國務院國資委宣傳局